In article <1138236773.796339.238420@g47g2000cwa.googlegroups.com>,
bgreer5050 <bgreer5050@yahoo.com> wrote:
>
>The very last thread of the post states:
>
> "A 40 square 10/12 roof
> with two roofs on it is going to take about 10-30 man-days just
> to tear off and clean up"
>
>Does this sound about right? It seems like a lot of man days.
Not really. It means a crew of 10 would take a day. I do not believe
the high end of the estimate, but the low end seems about right.
Dimitri
|
|